Stage One Consultation has now closed and SP Energy Networks has completed reviewing all the comments made to its proposed investment for installing a new 132kV wood pole overhead line from Oswestry to Wem.
Thank you to everyone who took time to visit one of our public events and / or responded with comments. These comments have resulted in an amended route for the new line – see the revised plan for further details.
Artist's impression of how the new line could look
The work carried out by SP Energy Networks and its advisers in reviewing the consultation responses and line route options is set out in two technical reports:
SP Energy Networks will seek to agree rights to construct and then operate and maintain the electricity apparatus installed with relevant landowners and occupiers. More on this is explained in our newsletter.
You can still contact us via our website, email address, FREEFONE or FREEPOST