Scotland is a world leader in the fight against climate change. We are producing more clean, green energy than ever before, and we need to strengthen the transmission network so we can get it to the homes, businesses, hospitals and public services that need it.
There is a substantial interest for renewable energy generation development (primarily wind and hydropower) and SP Energy Networks (SPEN) continues to receive associated grid connection requests from developers wishing to develop such renewable energy schemes.
SPEN have a license obligation to provide electricity generators with a connection to the electricity system in this area and, in line with this, is proposing to construct a new single circuit 132 kilovolt (kV) overhead line (OHL) to connect the proposed Hagshaw Hill Repowering Phase 3 Wind Farm and Bankend Rig III Wind Farm into the electricity network in South Lanarkshire Council area.
The Proposal
The Proposal
The Redshaw to Hagshaw Tee to Bankend Rig III Collector substation Overhead Line Grid Connection Project involves the construction of a new 132kV overhead line between Redshaw substation located about 4.5km south-east of Douglas, within South Lanarkshire and the proposed Bankend Rig III Collector substation via providing a tee point connection to Hagshaw Hill Repowering Phase 3 Wind Farm. The new overhead line connection will be around 38km, and the Hagshaw Tee line will be around 3km. The overhead line will be supported on trident wood poles.
Project Documents
Project Documents
Routeing and Consultation Document Supporting Figures’
Routeing and Consultation Document Supporting Figures
Have your say
Have your say
We are consulting the public on our proposals between 21st April and 26th May 2025.
You can view physical consultation materials and share feedback at the following events:
Wednesday 30 April, 2pm to 7pm - Sandford Village Hall, Strathaven Road, Sandford, Strathaven, ML10 6PE
Thursday 1 May, 1:30pm to 6:30pm - St Brides Centre, Braehead, Douglas, Lanark, ML11 0PT
You can also share your views by email at
RedshawToBankendRig@spenergynetworks.co.uk or write to:
Redshaw to Bankend Rig Project Manager
Land and Planning Team
SP Energy Networks
55 Fullarton Drive
Glasgow, G32 8FA
Feedback can also be provided via our online feedback form.
What happens next
What happens next
Following the first round of consultation we will develop a detailed design and alignment for the new project overhead line, including locations for wood poles, access routes and working areas. We will publish a report summarising the feedback received in this first round of consultation and how this has influenced our proposals.
We will carry out a detailed Environmental Impact Assessment (EIA) and also hold a second round of public events to information the public of our proposals.
After considering the feedback received in the second round of consultation, we will finalise our project proposals and submit consent applications to the Scottish Government’s Energy Consents Unit (SGECU), for consideration by Scottish Ministers. The Scottish Ministers will then undertake a final round of statutory consultation before making any decision on our applications.
The SGECU will then consider the proposals and representations before making any decision on our application.
Who is SP Energy Networks?
Who is SP Energy Networks?
SP Energy Networks is part of the ScottishPower Group. SP Transmission sits within SP Energy Networks and are responsible for the transmission of electricity in central and southern Scotland and the distribution network in parts of North West England and North Wales. Our role is to maintain, operate and invest in our network to secure a safe, reliable, and economic service for current and future consumers.
As a regulated utility provider, SP Energy Networks is obliged under the Electricity Act of 1989 to provide grid connection for electricity generated from power stations, windfarms, and various other utilities into our transmission network, which comprises over 4,000km of overhead lines and 320km of underground cable.
What statutory obligations does SP Energy Networks have?
What statutory obligations does SP Energy Networks have?
Our statutory legal obligations are set out in the Electricity Act 1989 and in our transmission licence.
We must develop and maintain an efficient coordinated and economical transmission system in accordance with security and quality of supply standards. We must offer to connect new power generators to the system and, make sure we keep disturbance to the natural and built environment and the people who live in it, work in it or enjoy it to a minimum.
Who regulates SP Energy Networks?
Who regulates SP Energy Networks?
We are regulated by Ofgem (Office of the Gas and Electricity Markets). Further information about Ofgem is available:
By emailing consumeraffairs@ofgem.gov.uk
Why is this project needed?
Why is this project needed?
SP Energy Networks received requests to connect the proposed wind farms (Bankend Rig III and Hagshaw Hill Repowering Phase 3) to the transmission grid in southern Scotland.
To comply with its statutory and license obligations, SP Energy Networks must provide such a connection. As with all the grid connections of this type, the initial premise is that these will be provided through OHLs.
What exactly are you proposing?
What exactly are you proposing?
We are proposing to construct a new c. 40km 132kV overhead line (OHL) between Redshaw substation and the proposed Bankend Rig III Collector substation via the provision of a connection to Hagshaw Hill Repowering Phase 3 substation near Douglas, South Lanarkshire.
The OHL is proposed to be supported by wooden trident poles with galvanised steekwork cross arms supporting aluminium conductors on insulators. These are suitable for supporting single circuit lines operating at 132kV.
Wood poles have a standard height above ground of approximately 11-16m, but these can be increased or reduced as required when circumstances dictate, e.g. over elevated land, structures or features.
The distance between wood poles will average between 80m and 100m but can be increased if there is requirement to span a larger landscape feature etc.
How much will the project cost?
How much will the project cost
It is early days and we won’t be able to cost the project fully until we have a defined proposal.
Who will pay for this project?
Who will pay for this project?
Ultimately, the cost of our investment in the electricity system is partly borne by consumers through electricity bills, so we are obliged to be economic and efficient. We recover our costs through transmission charges levied by National Grid.
The amount we invest in our networks and the amount we are able to recover is agreed with Ofgem, which is committed to working with industry, governments and consumer groups to deliver a net zero economy at the lowest cost to consumers. You can find out about Ofgem
Who gives you permission to construct new overhead lines?
Who gives you permission to construct new overhead lines?
We will be apply for consent under Section 37 of the Electricity Act 1989 to install the proposed overhead line. As such, applications will be submitted to the Scottish Government’s Energy Consents Unit, and Scottish Ministers will make the final decision whether to grant or refuse it.
When is the project needed by?
When is the project needed by?
We plan to have the project in operation by 2030, but there is a lot to do before then, such as environmental studies, designing the project, obtaining the necessary development consent, and building it.
How will the overhead line be constructed?
How will the overhead line be constructed?
The construction of OHLs requires additional temporary infrastructure accesses to poles location and construction compounds to store materials. All have limited maintenance requirements and are subject to well-established procedures for dismantling/decommissioning.
Following site preparation, small excavations are required to install each pole leg and its foundations which requires no concrete. The poles are then erected in sections before the conductors are ‘strung’ between them.
You can find more information about the construction process in our Routeing and Consultation Report
Can the new line go underground?
Can the new line go underground?
Under the Electricity Act 1989, SPEN is required to consider technical, economic and environmental matters, and reach a balance between them.
High voltage, high-capacity overhead lines are the proven economic and reliable choice for the bulk transmission of electricity throughout the world. Nevertheless, a section of underground cable is proposed as part of this connection due to technical constraints surrounding Redshaw Substation.
Section 9 of the Act places a duty on SPEN (as licence holder) to ‘develop and maintain and efficient, co-ordinated and economic system of electricity transmission/distribution’. In practice this means an overhead line will almost always be promoted ahead of an underground cable connection due to the higher cost of underground cabling for the relative voltages.
How are we consulting local people?
How are we consulting local people?
We are planning two rounds of public consultation before we submit our consent application to the Scottish Government.
The first round of consultation, from Monday 21st April to Monday 26th May 2025 is to seek people’s views on our preferred route for the proposed Redshaw to Hagshaw Tee to Bankend Rig III Collector substation OHL grid connection, and where the new line might go within that route.
Following this first round of consultation, we will develop a detailed design and alignment for the new connection overhead line, including locations for poles, access routes and working areas. We will publish a report summarising the feedback received in this first round of consultation and how this has influenced our proposals.
We will then hold a second round of public consultation, so that people can give us their views on the detailed route alignment. We will also carry out a detailed Environmental Impact Assessment at this stage.
After considering feedback received in the second round of consultation, we will finalise our proposals and submit applications for consent to the Scottish Ministers.
The Scottish Ministers will then hold a final round of statutory consultation before making any decision on our applications.
Are you consulting landowners?
Are you consulting landowners?
Yes, we are talking to owners and occupiers of land that might be affected by our preferred route. If you believe that your land may be affected and you have not heard from us, please contact us via email: RedshawToBankendRig@spenergynetworks.co.uk
Can you tell me more about Electric and Magnetic Fields (EMFs)?
Can you tell me more about Electric and Magnetic Fields (EMFs)?
Wherever electricity is used there will also be electric and magnetic fields. This is inherent in the laws of physics – we can modify the fields to some extent, but if we are going to use electricity, then EMFs are inevitable. Like many other things that we encounter in nature, EMFs can be harmful at high-enough levels. But the fields required, for example, to start interfering with the body’s nervous system are much greater than those produced by the UK electricity system. Hundreds of millions of pounds have been spent investigating this issue around the world. Research still continues to seek greater clarity; however, the balance of scientific evidence to date suggests that EMFs do not cause disease.
Electric and Magnetic fields – The Facts is a document produced by the UK electricity industry.
How do we provide feedback without a physical public consultation?
How do we provide feedback without a physical public consultation?
In the same way as a normal consultation event, you are able to provide feedback via email or post. The addresses can be found below:
If your question is not answered within these FAQs, you can email the mailbox at: RedshawToBankendRig@spenergynetworks.co.uk
Alternatively, you can write to:
Redshaw to Bankend Rig Project Manager,
Land and Planning Team,
SP Energy Networks
55 Fullarton Drive
Glasgow
G32 8FA