Skip to main content

Select Language:

Our RIIO-T2 Business Plan

T2 Business Plan front coverWe published our RIIO-T2 Business Plan in December 2019 to set out our vision and ambition for the transmission network in central and southern Scotland for the 2021-2026 period. This was based on a process of extensive engagement with stakeholders and users of the system. 

We've produced these pages as an update to our plan to show where the most material changes identified in Ofgem’s Final Determination of the RIIO-T2 are reflected through our plan. The updates you'll find on these pages don't re-state all of the detail of our original plan but provides a brief explanation of the notable changes and how the wider energy landscape has changed since the plan was published.

You can find all the information you need below - including links to our originally published plan and the updates following Ofgem's Final Determination.

Find out more about the T2 User Group

View a full list of the Medium Sized Investment Projects (MSIP) re-openers

Dec

An update on our plan

The challenges we identified in the plan continue to be relevant: 

  • Providing a leading role in Net Zero has become all the more important. This is evident through the national ambition for 40GW of offshore wind generation by 2030, of which more than 10GW is likely to be connected in Scotland that was unveiled since our plan was published. We've continued to see a growing volume of renewable generation seeking to connect to our system.     
  • As we've delivered our T1 plan, we've sought to identify further opportunities to improve efficiency and embed innovation. Since 2019 we've delivered further learnings from our deployment of digital substations. The learning from these has shaped our thinking for delivering the T2 plan to make sure we continue to maximise the value to consumers. 
  • The necessity for a resilient system has only become more apparent when we consider the impact of major interruptions to supply across Europe in January of this year, as well as rolling blackouts across Texas as a result of extreme weather leading to power shortages in February 2021. 
  • We have continued to make sure that consumers, network users and wider stakeholders are kept at the heart of our plans and decisions. This is evident through our decision to maintain the User Group that supported the co-creation of our plan, to have a group that can hold us accountable for delivering our plan and continue to shape our plan going forward.

Since the publication of our plan, we have also seen the impact of the COVID-19 pandemic. This has changed our operations through additional measures we take in our day to day activities. It's also had an impact of reducing demand for electricity which has placed new pressures on our network to make sure it continues to be operable.   

What's been accepted by Ofgem?

Following the publication of the plan, Ofgem undertook a detailed review of our proposals along with other electricity transmission owners to assess their justification and efficiency. Through this process, Ofgem have accepted 88% of the original expenditure that we had detailed in our plan

We were pleased to see that all but one of our projects were accepted and in recognition of the cost efficiency and ambition in the plan, a Business Plan Incentive reward of £5 million was awarded by Ofgem.

The project that was not accepted, the new Branxton substation in East Lothian will be resubmitted to Ofgem for review through the new uncertainty mechanisms. The changing nature of projects in this part of the network led to the details of this project changing at the time of Ofgem’s assessment. Some further minor changes were also made to the cost allowances

Our plan

To make sure our RIIO-T2 business plan was formed in the best interests of consumers, our network users and wider stakeholders, the SP Energy Networks Board have taken a proactive involvement in the creation and development of the plan from the outset.

Our Board Assurance Statement outlines the confidence and certainty in our ambitious and efficient proposals.

We also produced 36 supporting Annexes, which offer further detail and analysis on our overall plan – providing you with a further insight into the underpinning details.

More information

Watch our business plan launch video


What changed in our plan following Ofgem's Final Determination?

We've produced the sections below as an update to our plan to show where the most material changes identified in Ofgem’s Final Determination of the RIIO-T2 are reflected through our plan.  These updates don't re-state all of the detail of our original plan but provide a brief explanation of the notable changes made.

Innovation

The business plan contained a comprehensive innovation strategy that explained how past innovation had been considered in the creation of the business plan and a detailed a structured proposal for RIIO-T2 period, focused on Net Zero challenges.

The business plan proposed expenditure of £13.5 million related to the Network Innovation Allowance (NIA) and Ofgem have allowed this in full.

As described in Ofgem’s sector specific methodology, additional funding was available to roll out proven innovations and SPT submitted a proposal for £5.2 million of expenditure. However, Ofgem made a decision not to award this funding.

Environmentally Sustainable Network

Ofgem have approved our Environmental Action Plan and the associated funding.

We expect to publish our verified Science-Based Targets by the end of 2021.

We had proposed an Uncertainty Mechanism to cover the costs of delivering no net loss in biodiversity across the major networks projects in our baseline and to cover the cost of clean-up of legacy land contamination. In place of this, Ofgem provided us with a 'Use It or Lose It' allowance to cover such projects in T2. 

Various stakeholders had identified a lack of T2 incentive to encourage leadership in environmental impact reduction represented a significant gap at a time when the climate and biodiversity emergencies require accelerated action. Ofgem have responded to this by introducing an Environmental Scorecard symmetrical financial incentive.  We fully support this decision and believe that this Scorecard will allow us to focus internal action on priority environmental impact areas to drive better performance.

One of SPT’s Consumer Value Proposition (CVP) proposals was accepted by Ofgem at Final Determination: Maximise benefit from non-operational land. This CVP provides non-operational land to community groups to install up to 4MW of renewable generation and/or deliver biodiversity enhancements.

Net Zero Fund

In our business plan, we proposed a Net Zero Fund, similar to our RIIO-T1 Green Economy Fund.

This fund is intended to use our central and impartial role within the energy system to ensure local communities are financially supported to maximise the social and environment and economy benefits of local energy solutions. The fund will support the creation of local jobs, deliver significant carbon savings and support our communities. We estimated that for every £1 we spent, we could deliver £3 worth of value to the economy.  This fund was supported by our strategic stakeholders. Ofgem determined that the size of the fund should be reduced to £5 million. We are the only Transmission Operator to receive this funding.  

We will be working closely with our stakeholders during RIIO-T2 to ensure that this fund’s potential is maximised to ensure wider societal benefit.

Load Related Expenditure

The de-carbonisation of generation in Scotland has occurred rapidly and the introduction of legally-binding Net Zero targets set the backdrop to our load-related investment plan. All of the projects in our baseline plan were approved by Ofgem in the Final Determination with the exception of Branxton, which we discuss below.

We set out a high-confidence baseline of 900MW for the generation we expect to connect and proposed a suite of uncertainty mechanisms to allow the plan to respond to changes in our customers’ requirements. The uncertainty mechanism provided in the Final Determination provides us with the means to respond to changes in generation applying to connect to the system.

Following the recent publication of the Energy White Paper (Powering Our Net Zero Future) and NG ESO’s updated Future Energy Scenarios which now reflect Net Zero, we expect to make extensive use of the uncertainty mechanisms to fund projects that were not included in the baseline.

An integral part of our plans to connect offshore wind generation was the creation of a new substation at Branxton in East Lothian. The new substation will also act as the connection point of the proposed Eastern HVDC Link and resolve some thermal issues in that part of the network. While Ofgem agreed with the need case for substation, they have decided that it should be funded via uncertainty mechanisms. We will make the necessary application at the appropriate time in the substation’s development programme.

Our plan also included expenditure to create additional capacity for electricity demand. A key element of this was supporting electrification of the rail network by providing new connections and increasing the capacity at existing supply points. We included increases of the capacity of existing connections to the distribution system and the creation of new supply points in response to requests from SP Distribution. Our baseline plan was approved and there is an uncertainty mechanism which operates in the same way as the generation mechanism which will accommodate any changes our customers require.

The most recent Network Options Assessment recommended a significant increase in the level of reinforcement that’s required to meet Net Zero targets. While the majority of the works will complete after the end of RIIO-T2, we are forecasting an increase in expenditure in this area compared to our business plan. The uncertainty mechanisms that form part of the RIIO-T2 package provide us with the means to adapt our plan to deliver these works.

Non-load Related Expenditure

The costs associated with refurbishment and replacement of assets is known as non-load related. Our business plan detailed our planned interventions in the RIIO-T2 period, supported by detailed evidence, comprehensive justifications and external challenge and assurance.

Ofgem approved all of our baseline projects and we are well under way in delivering the early projects in the portfolio. We identified six projects that had a degree of uncertainty and proposed that these be subject to a re-opener uncertainty mechanism, which Ofgem accepted. We will submit applications when there is sufficient certainty over the scope and timing of the projects.

For some assets, the Network Asset Risk Methodology is used to set a target based on the long-term monetised risk benefit of the planned interventions. Our target, known as Baseline Network Risk Output (BNRO) has been set at £29.3 billion and this is calculated by adding the risk benefit of each of the individual asset interventions in our plan. The BNRO is R£200 million greater than our business plan submission. This is not because of any changes to our plan but because the method of calculating the total BNRO has changed since we submitted our plan.

 Supporting and Securing our network

Network Operations:

Our business plan reflected the changing nature of our network as new technology is integrated and the network extends, connecting new renewable generation and providing the additional network capability required. We also undertook a comprehensive review of our maintenance and inspection practices and ensured that we applied new and innovative techniques to improve effectiveness and efficiency. Our plan was accepted in full by Ofgem and the costs have been allowed in full.

Indirect Expenditure: 

Within our business plan we submitted our view of the support costs that will be required to ensure delivery of our planned network investment as well as support the drive towards Net Zero. This took the form of costs that are closely associated to the assets we deliver and those that support the wider business function.

In total these represented £273 million of out total expenditure in RIIO-2. As per the price control review process Ofgem made some adjustments to the allowance we had submitted in relation to workload volumes reductions in our Load and Non load delivery of £4.8m and general efficiency reductions as a result of industry wide benchmarking of £8.4 million. Therefore, as per Ofgem’s final determination our Indirect allowances have been set at £260 million representing a reduction of £13 million, or just under 5%.

Continuing to engage with Stakeholders

Our RIIO-T2 User Group was central to the development of that plan and provided crucial independent scrutiny and guidance during the development process, releasing their own independent report and assessment of our plans in December 2019.

The Group brought external representatives, independent experts and advisors – acting as a strong voice for our network users, customers and stakeholders during our decision-making processes.

Within our Business Plan we noted an intention to maintain the Transmission User Group throughout the RIIO-T2 period, providing the independent group with the opportunity to influence business decision making over the period, ensuring commitments are delivered and assessing performance.

Ofgem has not yet decided on a future enduring role or remit for these groups, however we have continued to set up the enduring group on the basis set out within the original business plan.  Following the conclusion of our Business Plan submission - former Energy Minister Rt Hon Charles Hendry stepped down as Chair of the Transmission User Group for SP Energy Networks. We are delighted that Angela Love has agreed to take up the position of Chair.

You can read more about our RIIO-T2 User Group here.

Managing Uncertainty

In developing the RIIO-T2 business plan, we only included baseline cost allowances where the need is clearly justified, timing of expenditure is understood, and costs are certain.

However, some areas of our operations naturally incur material costs which are difficult to forecast years ahead as they are subject to uncertainty outside our control. For these areas we proposed a suite of uncertainty mechanisms, both common and bespoke, to provide flexibility for the adjustment of revenues over the course of the T2 price control period.

Ofgem have sought to standardise uncertainty mechanisms as much as possible and we collaborated extensively with them and the other Transmission Owners to ensure each mechanism delivered optimal value for consumers whilst also facilitating the Governments ‘Net Zero’ ambitions. In the Final Determination the majority of our uncertainty mechanisms were accepted or repackaged under a new mechanism. A summary of the Uncertainty Mechanisms for T2 is shown below.

Expenditure area

Mechanism

Description

New connections

Generation/Demand Connections Volume Driver

Automatic volume driven process with bespoke rates for outputs relating to connection and network capacity, overhead lines and cable

<£100m Network reinforcements and atypical connections

Medium Sized Investment Projects Re-opener

Annual re-opener covering multiple investment areas. Single application per project with a value of <£100m.

Large network reinforcements

Large Onshore Transmission Investment (LOTI)

Multiple stage re-opener submission process for Load related investment greater than £100m.

Miscellaneous elements driven by external factors

Cyber Resilience, IT, Physical Security, visual mitigation re-opener

Various re-opener windows across RIIO-T2 for additional funding requests.

Authority Driven re-openers

Net Zero and Access Reform Change Re-opener 

Authority triggered re-opener to adjust allowances for ‘Net Zero’ development or changes arising from the Access reform review

Whole system

Whole System Co-ordinated Adjustment Mechanism (CAM)

In-period re-opener to reallocate responsibility for, and baseline revenue associated with, a CAM Activity to or from a Partner Licensee

Non-load

Uncertain Non-Load Related Re-opener

Annual re-opener for six named uncertain non-load related projects

Output Delivery Incentives

In developing our RIIO-T2 Output Delivery Incentive (ODI) proposals, we worked closely with stakeholders to identify the right incentives to help us maximise benefits for network customers, stakeholders and consumers as we continue to facilitate a Net-Zero future. SPT’s final incentive package contains seven incentives, six financial and one reputational.

These include our proposed Whole System ESO-TO Constraint Mitigation ODI, which has become the common SO:TO Optimisation ODI, and our Additional Contribution to the Low Carbon Transition ODI, which has been repackaged into the common Environmental Scorecard ODI.

Four bespoke incentive proposals were rejected by Ofgem at Final Determination, who took the view that these incentives were covered by other incentives or mechanisms or did not clearly evidence going beyond business as usual.

Relative to our T2 Business Plan, the maximum total reward and penalty from incentives has increased. The full list of T2 incentives can be found below, along with their financial value.

Output Delivery Incentive

Description

Annual Value   Range

Energy Not Supplied

Incentivises SPT to avoid Loss of Supply Events.

-£6.2m to +£1.3m

Insulation and Interruption Gas Emissions (IIG)

Incentivises SPT to maintain IIG leakage below our IIG leakage target.

+£0.1m to +£0.6m

Timely Connections

An incentive to ensure connection offers are provided in the timescales required by Ofgem.

-£6.2m to +£0m

Quality of Connections Satisfaction Survey

Incentivises SPT to improve our customer connection satisfaction survey scores. Year 1 has no penalty.

-£1.6m to +1.6m

Environmental Scorecard

Incentivises SPT to outperform against our Environmental Action Plan commitments, relative to environmental metrics.

Tbc

SO:TO Optimisation

Incentivises SPT to propose solutions to the ESO that make overall constraint cost savings. Trial incentive for years 1 and 2 only.

+£0m to +£2.5m

 

Total annual value:

-£9.2m to +£4.5m

The SO:TO Optimisation Incentive was introduced as a two-year trial at the start of RIIO-T2. Following the trial period, we have published an evaluation of the incentive as part of SPT's SO:TO Optimisation Incentive Final Report, available here.


Supporting Documentation & Additional Information

innovation
 

Navigating our RIIO-T2 Business Plan

This document provides a user-friendly overview of the SPEN RIIO-T2 Business Plan. We’ve outlined key elements of the plan, how they’re structured and added some key guidance points to help you navigate through the document.

innovation
 

Business Plan Summary

This Business Plan Summary document acts as an overview of the key points of our plan as well as discussing our ambitions, challenges and financial projections for the RIIO-T2 period.

innovation

Board Assurance Statement

This document sets out the Board Assurance Statement for the plan and details why we are confident that the content and associated costs have been tested for accuracy, ambition and efficiency.

 

Hi! I'm the SP Energy Networks System Agent, can I help you?