This is an accessible, text-only version of the New Connection Customer Process.
Stage 1 of 8: Make Your Enquiry
You make an enquiry about a connection via telephone, email or online form.
Stage 2 of 8: Submit Your Application
You can apply online using our new connection forms, or download a form and send it to us.
Stage 3 of 8: You Receive a Quote
We design your installation and send you a quote.
Stage 4 of 8: Make Your Payment
You accept the quote and arrange payment
Stage 5 of 8: Choose Your Meter Supplier
You choose an electricity supplier and give the MPAN details we provide. They will need this to fit your meter.
Stage 6 of 8: Agree Your Installation Date
We sort out any third party permission and arrange a date for the work to begin (usually around 6 weeks).
Read our Getting it Right: Wayleaves and Consents leaflet
Stage 7 of 8: We Complete Your Installation
We install your new connection point.
Stage 8 of 8: Your Supplier Installs Your Meter
Your supplier installs your meter and energises your supply.